6th September 2007
Dear Client …
I would like to provide you with an update on “Vila Verde - Santa Maria” construction progress.
Construction started, as promised, on September 2006.
Due to unexpected factors, namely sea port congestion, unavailability of aggregates and official
decision to relocate our concrete batch plant, we now find ourselves 5 months behind Schedule.
Nevertheless, we are working hard on a recovery plan in order to deliver the products within
contractual dates, taking into consideration these “force majeure” already mentioned.
We will also enable and provide, to your personal account in our system, two on-site cameras, which
will give you a more consistent means of checking on the construction progress. As you log in, the
link will be available on the Menu Bar under HELPDESK.
Please be assured that we will do our best to deliver on your expectation for a quality home in Cape
Verde, as promised.
Kind Regards,
Nuno M. Martins
Sales Manager